1.1 This standard is regarded as the basis for selecting parameters and capacity in purchasing thermal generator sets. It is applicable to condensing turbine (power is 3-600MW) and matched steam boiler and turbo-generator; it is not applicable to heating turbine, geothermal turbine, waste heat boiler, hydro-generator and generator driven by other modes.
1.2 This standard is based on thermal generator set parameter standard issued in Document (72)Yi Ji Dian Lian Zi No. 911 and (72)Shui Dian Zong Zi No. 284, and supplemented properly according to set developing conditions in recent years.
1.3 Turbine, boiler and generator TCST of Ministry of Water Resources and Electric Power are in charge of the explanation of this standard according to different professions.
1 General provisions
2 Parameter series of fixed power plant turbine
3 Parameter series of power plant boiler
4 Parameter series of generator
Annex 1 Compilation explanation of parameter series of fixed power plant turbine
Annex 2 Compilation explanation of parameter series of power plant boiler
Annex 3 Compilation explanation of parameter series of generator
Standard
SD 264-1988 Standard of Parameters for Steam Turbine, Boiler and Turbine Generator in Thermal Power Plant (English Version)
Standard No.
SD 264-1988
Status
valid
Language
English
File Format
PDF
Word Count
3000 words
Price(USD)
60.0
Implemented on
1987-11-24
Delivery
via email in 1 business day
Detail of SD 264-1988
Standard No.
SD 264-1988
English Name
Standard of Parameters for Steam Turbine, Boiler and Turbine Generator in Thermal Power Plant
1.1 This standard is regarded as the basis for selecting parameters and capacity in purchasing thermal generator sets. It is applicable to condensing turbine (power is 3-600MW) and matched steam boiler and turbo-generator; it is not applicable to heating turbine, geothermal turbine, waste heat boiler, hydro-generator and generator driven by other modes.
1.2 This standard is based on thermal generator set parameter standard issued in Document (72)Yi Ji Dian Lian Zi No. 911 and (72)Shui Dian Zong Zi No. 284, and supplemented properly according to set developing conditions in recent years.
1.3 Turbine, boiler and generator TCST of Ministry of Water Resources and Electric Power are in charge of the explanation of this standard according to different professions.
Contents of SD 264-1988
1 General provisions
2 Parameter series of fixed power plant turbine
3 Parameter series of power plant boiler
4 Parameter series of generator
Annex 1 Compilation explanation of parameter series of fixed power plant turbine
Annex 2 Compilation explanation of parameter series of power plant boiler
Annex 3 Compilation explanation of parameter series of generator