1 General Provisions
1.0.1 This code is formulated with view to standardizing the green construction of building, achieving resource saving and environmental protection, and guaranteeing the safety and health of construction personnel.
1.0.2 This code is applicable to the green construction of constructed, extended, renovated or dismantled buildings.
1.0.3 In addition to those specified in this code, the green construction of building also shall comply with the requirements stipulated in the current relevant standards of the nation.
2 Terms
2.0.1 Green construction
The building construction activity that is able to maximally save resources, decrease negative effect on the environment and therefore realize "Four Savings and One Environmental Protection" (energy saving, material saving, water saving, land saving and environmental protection) with the aid of scientific management and advanced technology, under the premise that the basic requirements such as quality and safety are ensured.
2.0.2 Construction trash
Waste materials arising from the construction, extension, renovation and dismantlement of various buildings, structures and pipe networks as well as the decoration of buildings.
2.0.3 Building waste
Construction trash which loses the recycling value on construction site after being classified.
2.0.4 Green construction evaluation
The evaluation activity on the level and effect of green construction of building.
2.0.5 Information construction
The construction mode in which the information during implementation process of engineering project is orderly stored, treated, transmitted and fed back by using such information means as computer, network and database.
2.0.6 Construction industrialization
The construction mode in which the building members and accessories are manufactured in plant and are installed at the construction site in manner of modern industrial production.
1 General Provisions
2 Terms
3 Basic Requirements
3.1 Organization and Management
3.2 Resources Saving
3.3 Environmental Protection
4 Construction Preparation
5 Construction Site
5.1 General Requirements
5.2 General Layout
5.3 Enclosing Wall and Road Works
5.4 Temporary Facilities
6 Foundation Engineering
6.1 General Requirements
6.2 Earthwork and Rockwork
6.3 Piled Foundation
6.4 Foundation Treatment
6.5 Groundwater Control
7 Main Structure Engineering
7.1 General Requirements
7.2 Concrete Engineering
7.3 Masonry Engineering
7.4 Steel Structure Engineering
7.5 Other Items
8 Decoration Engineering
8.1 General Requirements
8.2 Ground Engineering
8.3 Door, Window and Curtain Wall Works
8.4 Ceiling Works
8.5 Partition and Inner Wall Works
9 Heat-insulating and Water-proofing Engineering
9.1 General Requirements
9.2 Heat-insulating Engineering
9.3 Water-proofing Engineering
10 Electromechanical Fixing Engineering
10.1 General Requirements
10.2 Pipeline Engineering
10.3 Ventilation Engineering
10.4 Electrical Engineering
11 Dismantling Engineering
11.1 General Requirements
11.2 Dismantling Preparation
11.3 Dismantling Work
11.4 Comprehensive Utilization
Explanation of Wording in This Code
List of Quoted Standards
1 General Provisions
1.0.1 This code is formulated with view to standardizing the green construction of building, achieving resource saving and environmental protection, and guaranteeing the safety and health of construction personnel.
1.0.2 This code is applicable to the green construction of constructed, extended, renovated or dismantled buildings.
1.0.3 In addition to those specified in this code, the green construction of building also shall comply with the requirements stipulated in the current relevant standards of the nation.
2 Terms
2.0.1 Green construction
The building construction activity that is able to maximally save resources, decrease negative effect on the environment and therefore realize "Four Savings and One Environmental Protection" (energy saving, material saving, water saving, land saving and environmental protection) with the aid of scientific management and advanced technology, under the premise that the basic requirements such as quality and safety are ensured.
2.0.2 Construction trash
Waste materials arising from the construction, extension, renovation and dismantlement of various buildings, structures and pipe networks as well as the decoration of buildings.
2.0.3 Building waste
Construction trash which loses the recycling value on construction site after being classified.
2.0.4 Green construction evaluation
The evaluation activity on the level and effect of green construction of building.
2.0.5 Information construction
The construction mode in which the information during implementation process of engineering project is orderly stored, treated, transmitted and fed back by using such information means as computer, network and database.
2.0.6 Construction industrialization
The construction mode in which the building members and accessories are manufactured in plant and are installed at the construction site in manner of modern industrial production.
Contents of GB/T 50905-2014
1 General Provisions
2 Terms
3 Basic Requirements
3.1 Organization and Management
3.2 Resources Saving
3.3 Environmental Protection
4 Construction Preparation
5 Construction Site
5.1 General Requirements
5.2 General Layout
5.3 Enclosing Wall and Road Works
5.4 Temporary Facilities
6 Foundation Engineering
6.1 General Requirements
6.2 Earthwork and Rockwork
6.3 Piled Foundation
6.4 Foundation Treatment
6.5 Groundwater Control
7 Main Structure Engineering
7.1 General Requirements
7.2 Concrete Engineering
7.3 Masonry Engineering
7.4 Steel Structure Engineering
7.5 Other Items
8 Decoration Engineering
8.1 General Requirements
8.2 Ground Engineering
8.3 Door, Window and Curtain Wall Works
8.4 Ceiling Works
8.5 Partition and Inner Wall Works
9 Heat-insulating and Water-proofing Engineering
9.1 General Requirements
9.2 Heat-insulating Engineering
9.3 Water-proofing Engineering
10 Electromechanical Fixing Engineering
10.1 General Requirements
10.2 Pipeline Engineering
10.3 Ventilation Engineering
10.4 Electrical Engineering
11 Dismantling Engineering
11.1 General Requirements
11.2 Dismantling Preparation
11.3 Dismantling Work
11.4 Comprehensive Utilization
Explanation of Wording in This Code