1.0.1 This provision specifies the work of instrumentation in each stage of engineering project and make the work scope and responsibilities of instrumentation clear.
1.0.2 This provision is applicable to the work of instrumentation in each stage of design, procurement, construction, starting, assessment and acceptance as well as design control, foundation works and technical development.
1.0.3 During the implementation of this provision, the provisions of current relevant national standard shall be conformed too.
2 Preliminary Work of Design
2.1 Feasibility Study (Including Preliminary Feasibility Study)
2.1.1 At the feasibility study stage, the instrumentation is in charge of studying out the following work:
1 Automation level;
2 Selection principle of main instrument;
3 Propose the instrument investment estimation conditions;
4 Propose compile conditions of feasibility research report to relevant professions.
2.1.2 Accomplish the feasibility study report of this profession.
2.2 Engineering Quotation
2.2.1 At the engineering quotation stage, the instrumentation is in charge of studying out the following work:
1 Control scheme;
2 Design principles, accepted standard and regulation;
3 Instrument selection;
4 Assist the budget estimate profession to estimate equipment cost and material expenses;
5 Estimation of work amount and cost of design and installation;
6 Propose compile conditions of engineering quotation to relevant professions.
2.2.2 Accomplish the engineering quotation records on this profession.
3 Project Introducing
3.0.1 At the introducing project stage, the instrumentation is in charge of the following work:
1 Take part in the technical exchange with foreign businessman;
2 Take charge of the negotiation on the technical Appendix of contract. Propose terms of design principles, supply scope, batch delivery of equipment, design division and design document, discuss the name list of supply manufacturer recommended by foreign side;
3 Take part in the work of design communication, equipment check and design audit;
4 Take part in the work of cooperative design, returned bag design and DCS software configuration.
Standard
HG/T 20636.1-1998 Work scope and responsibilities of instrumentation (English Version)
Standard No.
HG/T 20636.1-1998
Status
superseded
Language
English
File Format
PDF
Word Count
1500 words
Price(USD)
429.0
Implemented on
1999-1-1
Delivery
via email in 1 business day
Detail of HG/T 20636.1-1998
Standard No.
HG/T 20636.1-1998
English Name
Work scope and responsibilities of instrumentation
1 General Provisions
1.0.1 This provision specifies the work of instrumentation in each stage of engineering project and make the work scope and responsibilities of instrumentation clear.
1.0.2 This provision is applicable to the work of instrumentation in each stage of design, procurement, construction, starting, assessment and acceptance as well as design control, foundation works and technical development.
1.0.3 During the implementation of this provision, the provisions of current relevant national standard shall be conformed too.
2 Preliminary Work of Design
2.1 Feasibility Study (Including Preliminary Feasibility Study)
2.1.1 At the feasibility study stage, the instrumentation is in charge of studying out the following work:
1 Automation level;
2 Selection principle of main instrument;
3 Propose the instrument investment estimation conditions;
4 Propose compile conditions of feasibility research report to relevant professions.
2.1.2 Accomplish the feasibility study report of this profession.
2.2 Engineering Quotation
2.2.1 At the engineering quotation stage, the instrumentation is in charge of studying out the following work:
1 Control scheme;
2 Design principles, accepted standard and regulation;
3 Instrument selection;
4 Assist the budget estimate profession to estimate equipment cost and material expenses;
5 Estimation of work amount and cost of design and installation;
6 Propose compile conditions of engineering quotation to relevant professions.
2.2.2 Accomplish the engineering quotation records on this profession.
3 Project Introducing
3.0.1 At the introducing project stage, the instrumentation is in charge of the following work:
1 Take part in the technical exchange with foreign businessman;
2 Take charge of the negotiation on the technical Appendix of contract. Propose terms of design principles, supply scope, batch delivery of equipment, design division and design document, discuss the name list of supply manufacturer recommended by foreign side;
3 Take part in the work of design communication, equipment check and design audit;
4 Take part in the work of cooperative design, returned bag design and DCS software configuration.