1.0.1 This Code is compiled for construction quality of industrial boiler and hot water boiler installation engineering and promoting installation technological advances.
1.0.2 This code is applied to the installation of field-installed fixed-type steam boiler and fixed-type pressurized hot water boiler when water is mediator and rated operating pressure is not higher 2.5MPa. For the boiler that leaves the factory in a whole, its installation can be carirried out according to this code. However, this code is not applied to the installation of cast iron boiler, the boiler in the vehicles and ship, electrically heated boiler and nuclear energy boiler.
1.0.3 Boiler installation contractor must hold the boiler installation permit issued by provincial board of labour, coincident with the installation style and boiler level.
1.0.4 Before or during the boiler installation process, the installation must cease if the components in compression have quality problem and effect safe handling.
1.0.5 Besides this code, the construction and acceptance of industrial boiler installation shoud be conducted according to others current relative standard specifications.
Standard
GB 50273-1998 Code for Construction and Acceptance of Industrial Boiler Installa (English Version)
Standard No.
GB 50273-1998
Status
superseded
Language
English
File Format
PDF
Word Count
17000 words
Price(USD)
420.0
Implemented on
1998-12-1
Delivery
via email in 1 business day
Detail of GB 50273-1998
Standard No.
GB 50273-1998
English Name
Code for Construction and Acceptance of Industrial Boiler Installa
1.0.1 This Code is compiled for construction quality of industrial boiler and hot water boiler installation engineering and promoting installation technological advances.
1.0.2 This code is applied to the installation of field-installed fixed-type steam boiler and fixed-type pressurized hot water boiler when water is mediator and rated operating pressure is not higher 2.5MPa. For the boiler that leaves the factory in a whole, its installation can be carirried out according to this code. However, this code is not applied to the installation of cast iron boiler, the boiler in the vehicles and ship, electrically heated boiler and nuclear energy boiler.
1.0.3 Boiler installation contractor must hold the boiler installation permit issued by provincial board of labour, coincident with the installation style and boiler level.
1.0.4 Before or during the boiler installation process, the installation must cease if the components in compression have quality problem and effect safe handling.
1.0.5 Besides this code, the construction and acceptance of industrial boiler installation shoud be conducted according to others current relative standard specifications.