1 Scope
This Standard specifies the requirements of testing test conditions, testing items (including type test and delivery inspection) and testing methods, testing result judgement methods and inspection cycle of time synchronism systems for power system.
This Standard is applicable to the testing of time synchronism systems for power system, may be used as inspection reference for development, production and inspection department of time-synchronization-type products for power system and may be referred by field inspection of operation department.
2 Normative Reference
The following referenced documents are indispensable for the application of this document. For dated references, only the editions cited apply. For undated references, the latest editions of the normative document (including any amendments) apply.
GB/T 7261-2008 Basic Testing Method for Relaying Protection and Security Automatic Equipment
GB/T 13729-2002 Remote Terminal Unit Equipment
GB/T 17626.2-2006 Electromagnetic Compatibility - Testing and Measurement Techniques-Electrostatic Discharge Immunity Test
GB/T 17626.3-2006 Electromagnetic Compatibility - Testing and Measurement Techniques-Radiated Radio-frequency Electromagnetic Field Immunity Test
GB/T 17626.4—2008 Electromagnetic Compatibility - Testing and Measurement Techniques - Electrical Fast Transient/Burst Immunity Test
GB/T 17626.5- 2008 Electromagnetic Compatibility - Testing and Measurement Techniques – Surge (impact) Immunity Test
GB/T 17626.8-2006 Electromagnetic Compatibility - Testing and Measurement Techniques-Power Frequency Magnetic Field Immunity Test
GB/T 17626.9-1998 Electromagnetic Compatibility - Testing and Measurement Techniques - Pulse Magnetic Field Immunity Test
GB/T 17626.10-1998 Electromagnetic Compatibility - Testing and Measurement Techniques-Damped Oscillatory Magnetic Field Immunity Test
GB/T 17626.12-1998 Electromagnetic Compatibility - Testing and Measurement Techniques-Oscillatory Waves Immunity Test
GB/T 19520.12-2009 Mechanical Structures for Electronic Equipment - Dimensions of Mechanical Structures of the 482.6 mm (19 in) Series - Part 3-101: Subracks and Associated Plug-in Units
DL/T 1100.1-2009 Time Synchronism Systems of Power System Part 1: Technical Specifications
3 Terminologies and Definitions
Foreword I
1 Scope
2 Normative Reference
3 Terminologies and Definitions
4 Testing Items and Requirements
5 Inspection Rules
Appendix A (Informative) On-site Test
1 Scope
This Standard specifies the requirements of testing test conditions, testing items (including type test and delivery inspection) and testing methods, testing result judgement methods and inspection cycle of time synchronism systems for power system.
This Standard is applicable to the testing of time synchronism systems for power system, may be used as inspection reference for development, production and inspection department of time-synchronization-type products for power system and may be referred by field inspection of operation department.
2 Normative Reference
The following referenced documents are indispensable for the application of this document. For dated references, only the editions cited apply. For undated references, the latest editions of the normative document (including any amendments) apply.
GB/T 7261-2008 Basic Testing Method for Relaying Protection and Security Automatic Equipment
GB/T 13729-2002 Remote Terminal Unit Equipment
GB/T 17626.2-2006 Electromagnetic Compatibility - Testing and Measurement Techniques-Electrostatic Discharge Immunity Test
GB/T 17626.3-2006 Electromagnetic Compatibility - Testing and Measurement Techniques-Radiated Radio-frequency Electromagnetic Field Immunity Test
GB/T 17626.4—2008 Electromagnetic Compatibility - Testing and Measurement Techniques - Electrical Fast Transient/Burst Immunity Test
GB/T 17626.5- 2008 Electromagnetic Compatibility - Testing and Measurement Techniques – Surge (impact) Immunity Test
GB/T 17626.8-2006 Electromagnetic Compatibility - Testing and Measurement Techniques-Power Frequency Magnetic Field Immunity Test
GB/T 17626.9-1998 Electromagnetic Compatibility - Testing and Measurement Techniques - Pulse Magnetic Field Immunity Test
GB/T 17626.10-1998 Electromagnetic Compatibility - Testing and Measurement Techniques-Damped Oscillatory Magnetic Field Immunity Test
GB/T 17626.12-1998 Electromagnetic Compatibility - Testing and Measurement Techniques-Oscillatory Waves Immunity Test
GB/T 19520.12-2009 Mechanical Structures for Electronic Equipment - Dimensions of Mechanical Structures of the 482.6 mm (19 in) Series - Part 3-101: Subracks and Associated Plug-in Units
DL/T 1100.1-2009 Time Synchronism Systems of Power System Part 1: Technical Specifications
3 Terminologies and Definitions
Contents of GB/T 26866-2011
Foreword I
1 Scope
2 Normative Reference
3 Terminologies and Definitions
4 Testing Items and Requirements
5 Inspection Rules
Appendix A (Informative) On-site Test