1.0.1 This code is developed in order to improve the construction level of the conveyor equipment installation engineering, promote the technological progress, ensure the engineering quality and safety and improve the economic performance.
1.0.2 This code applies to the construction and acceptance of the installation engineering of belt conveyor, slat conveyor equipment, vertical bucket elevator, screw conveyor, roller conveyor, overhead conveyor, vibrating conveyor, en-masse conveyer, pneumatic conveyor as well as mine hoist and winch.
1.0.3 In addition to this code, the construction and acceptance of conveyor equipment installation engineering still shall be in accordance with those specified in the current relevant national standards.
1 General Provisions
2 Basic Requirement
3 Belt Conveyor
4 Slat Conveyor Equipment
4.1 Slat Conveyer
4.2 Light-duty Slat Feeder
4.3 Middle-duty Slat Feeder
4.4 Heavy-duty Slat Feeder
4.5 Test Run
5 Vertical Bucket Elevator
6 Screw Conveyor
7 Roller Conveyor
8 Overhead Conveyer
9 Vibrating Conveyor
10 En-masse Conveyer
11 Pneumatic Conveyor
12 Mine Hoist & Winch
12.1 Winding Mine Hoist & Winch
12.2 Multi-rope Hoist
12.3 Other Winches
12.4 Test Run
13 Acceptance
Appendix A: Belt Connecting Method for Belt Conveyor
Explanation of Wording in this Code
List of Quoted Sandards
1.0.1 This code is developed in order to improve the construction level of the conveyor equipment installation engineering, promote the technological progress, ensure the engineering quality and safety and improve the economic performance.
1.0.2 This code applies to the construction and acceptance of the installation engineering of belt conveyor, slat conveyor equipment, vertical bucket elevator, screw conveyor, roller conveyor, overhead conveyor, vibrating conveyor, en-masse conveyer, pneumatic conveyor as well as mine hoist and winch.
1.0.3 In addition to this code, the construction and acceptance of conveyor equipment installation engineering still shall be in accordance with those specified in the current relevant national standards.
Contents of GB 50270-2010
1 General Provisions
2 Basic Requirement
3 Belt Conveyor
4 Slat Conveyor Equipment
4.1 Slat Conveyer
4.2 Light-duty Slat Feeder
4.3 Middle-duty Slat Feeder
4.4 Heavy-duty Slat Feeder
4.5 Test Run
5 Vertical Bucket Elevator
6 Screw Conveyor
7 Roller Conveyor
8 Overhead Conveyer
9 Vibrating Conveyor
10 En-masse Conveyer
11 Pneumatic Conveyor
12 Mine Hoist & Winch
12.1 Winding Mine Hoist & Winch
12.2 Multi-rope Hoist
12.3 Other Winches
12.4 Test Run
13 Acceptance
Appendix A: Belt Connecting Method for Belt Conveyor
Explanation of Wording in this Code
List of Quoted Sandards