Fire resistance test for lift landing doors - Methods of measuring integrity, thermal insulation and heat flux
1 Scope
This standard specifies the terms and definitions, fire resistance codes and rating, test apparatus, test piece conditions, test piece preparation, test procedures, test results, validity of test results and test reports, etc. on general method of fire resistance test for lift landing doors.
It is applicable to all types of lift landing doors.
2 Normative references
The following referenced documents are indispensable for the application of this document. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.
GB/T 5907 Fundamental terminology of fire protection - Part 1
GB/T 14107 Fundamental terminology of fire protection - Part 2
GB 7588 Safety rules for the construction and installation of electric lifts
GB/T 7633 Fire resistance tests - Door and shutter assemblies
GB/T 9978.1 Fire-resistance tests - Elements of building construction - Part 1: General requirements
3 Terms and definitions
For the purposes of this document, the terms and definitions given in GB/T 5907, GB/T 14107 and GB/T 9978.1 and the following apply.
3.1
lift landing door
door installed at the opening on each floor of the lift shaft for people to enter and exit the lift
3.2
insulated lift landing door
lift landing door which can meet the requirements of fire integrity and fire insulation at the same time within a certain time
Foreword i
1 Scope
2 Normative references
3 Terms and definitions
4 Fire resistance codes and rating
5 Test apparatus
6 Test conditions
7 Test piece preparation
8 Test procedures
9 Test results
10 Validity of test result
11 Test report
Fire resistance test for lift landing doors - Methods of measuring integrity, thermal insulation and heat flux
1 Scope
This standard specifies the terms and definitions, fire resistance codes and rating, test apparatus, test piece conditions, test piece preparation, test procedures, test results, validity of test results and test reports, etc. on general method of fire resistance test for lift landing doors.
It is applicable to all types of lift landing doors.
2 Normative references
The following referenced documents are indispensable for the application of this document. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.
GB/T 5907 Fundamental terminology of fire protection - Part 1
GB/T 14107 Fundamental terminology of fire protection - Part 2
GB 7588 Safety rules for the construction and installation of electric lifts
GB/T 7633 Fire resistance tests - Door and shutter assemblies
GB/T 9978.1 Fire-resistance tests - Elements of building construction - Part 1: General requirements
3 Terms and definitions
For the purposes of this document, the terms and definitions given in GB/T 5907, GB/T 14107 and GB/T 9978.1 and the following apply.
3.1
lift landing door
door installed at the opening on each floor of the lift shaft for people to enter and exit the lift
3.2
insulated lift landing door
lift landing door which can meet the requirements of fire integrity and fire insulation at the same time within a certain time
Contents of GB/T 27903-2011
Foreword i
1 Scope
2 Normative references
3 Terms and definitions
4 Fire resistance codes and rating
5 Test apparatus
6 Test conditions
7 Test piece preparation
8 Test procedures
9 Test results
10 Validity of test result
11 Test report