This Part of GB/T 16507 specifies the water-tube boiler proper and the requirements for installation, commissioning, quality acceptance and operation, etc. of the boiler external tubes.
This Part is applicable to the water-tube boiler as defined in GB/T 16507.1.
Foreword i 1 Scope 2 Normative References 3 Terms and Definitions 4 Basic Requirements 5 Foundation, Support and Steel Structure 6 Boiler Drum (Start-up Separator) and Header, Desuperheater 7 Heating Surface 8 Air Preheater 9 Boiler External Pipes and Safety Accessories 10 Combustion Equipment 11 Auxiliary Device 12 Platform, Escalator and Railing 13 Hydraulic Test 14 Boiler Wall Building, Pouring and Thermal Insulation 15 Chemical Cleaning, Washing and Purging 16 Commissioning 17 Quality Acceptance 18 Operation
This Part of GB/T 16507 specifies the water-tube boiler proper and the requirements for installation, commissioning, quality acceptance and operation, etc. of the boiler external tubes.
This Part is applicable to the water-tube boiler as defined in GB/T 16507.1.
Contents of GB/T 16507.8-2013
Foreword i
1 Scope
2 Normative References
3 Terms and Definitions
4 Basic Requirements
5 Foundation, Support and Steel Structure
6 Boiler Drum (Start-up Separator) and Header, Desuperheater
7 Heating Surface
8 Air Preheater
9 Boiler External Pipes and Safety Accessories
10 Combustion Equipment
11 Auxiliary Device
12 Platform, Escalator and Railing
13 Hydraulic Test
14 Boiler Wall Building, Pouring and Thermal Insulation
15 Chemical Cleaning, Washing and Purging
16 Commissioning
17 Quality Acceptance
18 Operation